Contract Signed for Cranmore Regeneration Project, Phase 3

Contract Signed for Cranmore Regeneration Project, Phase 3 Back row (left to right): DOS Jim Molloy, Senior Architect Marian O’Callaghan, Executive Technician Frank Quinn, Senior Executive Architect Míċeál McGinty, Executive Architect Colin Bell, Gary O’Connor Associate Rhatigan Architects.
Front row (left to right): Fergal Meagher Managing Director Kilcawley Construction, An Cathaoirleach Councillor Declan Bree and Chief Executive Martin Lydon

Sligo County Council is delighted to confirm that the Contract for the Cranmore Regeneration Project, Phase 3 - Building & Environmental Upgrade Works has been awarded to Kilcawley Construction.

It is planned for the work to be carried out in 5 stages, with a duration of approximately 24 months.

This project represents the final phase of the deep retrofit, energy works to upgrade residents’ homes in Cranmore. On completion of the project, residents’ homes will achieve an ‘A Building Energy Rating - BER’.

Cathaoirleach Councillor Declan Bree said

This final phase of the deep retrofit and energy upgrade works in Cranmore is a testament to our commitment to improving the lives of our residents. Upon completion, their homes will achieve an 'A Building Energy Rating - BER,' reflecting the Councils dedication to sustainability and energy efficiency.