Taking in Charge
Taking in Charge Fees
Taking In Charge fees are as follows:
Category | No. of Dwellings Housing Developments | Fee per Dwelling |
---|---|---|
1 | Up to 25 units | €250 per dwelling house |
2 | From 26 units to 50 units inclusive | €225 per dwelling house (min. charge €6,400) |
3 | From 51 units to 75 units inclusive | €200 per dwelling house (min. charge €11,400) |
4 | Over 75 units | €175 per dwelling house (min. charge €15,100) |
Taking in Charge Application form
The application form for Taking in Charge is available to download below.
Download Taking In Charge Application Form (PDF) - 27 kbs
Taking in Charge Policy
The policy document for Sligo County Council for Taking in Charge is available below.
Download Policy on Taking in Charge of Residential Development (PDF) - 63 kbs
Release / Refund of Bond
When permission is granted for a development, the planning authority may attach a condition requiring the lodgement of a cash sum or an insurance company bond which will be called upon to carry out any works required in the event of a developer failing to complete the development to the required standard.
It is the policy of the council to ensure that all bonds remain in place until the development is completed to the satisfaction of the planning authority as per the condition of planning. When submitting a bond, it must be in accordance with the approved bond format as per the link below.
When applying to release a bond, the developer is required to complete a release of bond application.